A Bird Key resident wrote to the city this month with a simple question: what is actually happening to the park and the road out front. The letter, printed in Longboat Key News's September 11 roundup of reader mail, described dirt piles that had started growing grass, equipment sitting untouched for weeks, and a new work zone outside the Ritz-Carlton that had closed off the crosswalk pedestrians use to cross toward St. Armands. The writer wasn't alone in noticing. Anyone who crosses the John Ringling Causeway to get on or off the island has watched the same scene unfold since late December.
Here's what most of that watching has missed. This isn't a pothole repair that stalled. It's the first time in the causeway's history that Bird Key Drive, Golden Gate Drive, and Sunset Drive will get actual traffic signals. Right now, all three intersections run on stop signs and the kind of informal right of way that works until it doesn't. When this project wraps, that changes for good. The slow, confusing, dirt pile phase everyone's driving past is the price of a fix that's been overdue since the bridge itself opened in 2003.
The Florida Department of Transportation began construction on State Road 789, the stretch of the John Ringling Causeway between Bird Key Drive and Sunset Drive, on December 28, 2025. It's a $12.3 million project, and the scope goes well past resurfacing. According to FDOT's own fact sheet, the work includes:
That last detail explains some of what residents have been seeing at ground level. The trees along the causeway aren't being removed. They're being moved, and the temporary staging for that work looks a lot like neglect if you don't know what it is.
The signal work is the part worth sitting with. Bird Key Drive, Golden Gate Drive, and Sunset Drive have functioned on stop signs and driver judgment for as long as the current high-span bridge has existed, which is more than two decades. That arrangement has been manageable because Bird Key is a small, low-traffic community of roughly 500 homes. It has also meant that the single road connecting the island to the mainland, and the same road that serves as the barrier islands' hurricane evacuation route, has relied on drivers reading each other correctly at three unsignalized crossings.
| Intersection | Current control | What's coming |
|---|---|---|
| Bird Key Drive | Stop sign, informal right of way | Full traffic signal |
| Golden Gate Drive | Stop sign, informal right of way | Full traffic signal |
| Sunset Drive | Stop sign, informal right of way | Full traffic signal |
Golden Gate Drive sits closest to the Ritz-Carlton, which is likely why that stretch is where residents have noticed the crosswalk closure and the heaviest equipment staging. It's also one of the three intersections getting a signal, so the disruption there isn't incidental. It's the leading edge of the part of the project that changes the most.
If you've tried to find a firm end date for this project, you've probably found more than one answer, and they don't match. The Coalition of City Neighborhood Associations, citing FDOT's own project announcement, lists an estimated completion of early 2027. FDOT's Sarasota County RoadWatch page, the one that updates week to week, currently reads that completion remains on track for late 2026. FDOT's districtwide RoadWatch page still shows early 2027 for the same corridor. None of the three sources has been corrected to match the others.
The honest answer for anyone planning a season, a renovation, or just a daily commute around this is to expect the back half of 2026 into the first months of 2027, and to check the Sarasota County RoadWatch page for the current week's status rather than anchoring to whichever estimate happens to be circulating that month. It's a small thing, but it matters if you're trying to time a project, a move, or even a dinner reservation at St. Armands Circle around lane closures that shift by the week.
While the signals get built, the rules of the road here have already changed. The posted speed limit through the corridor, on both Gulfstream Avenue and the causeway itself, has been reduced to 35 miles per hour for the duration of construction. Speeding fines double anywhere in the work zone when crews are present, a detail FDOT has repeated in every project update since work began. Lane closures come and go depending on the project's phase, sometimes overnight, sometimes during the day, and noise from pumps and equipment can carry after dark as easily as during working hours.
Pedestrians and cyclists should expect posted detours rather than the paths they're used to. The walking route beneath the bridge near Bird Key Park has been affected by the construction staging, and the Coalition of City Neighborhood Associations has specifically noted that pedestrians should follow posted detour signs rather than assume the usual route is open. If you're timing a walk, a run, or a bike ride over the Ringling Bridge, that's worth building into your plans for the next several months.
There's one upside worth knowing about if you rely on transit. The City of Sarasota has separately flagged a bus shoulder addition on the bridge for its free Bay Runner trolley, which will be permitted to use the shoulder once traffic slows to 15 miles per hour or below. During season traffic, when the causeway backs up the way it always has around St. Armands Circle, that shoulder gives the trolley a way around the worst of it. It's a small addition, but it's the kind of detail that only shows up if you're reading the project documents rather than driving past the cones.
The frustration in that letter to the city makes sense. Watching dirt sit and grow grass while a crosswalk stays blocked doesn't look like progress. But the project underneath that frustration is genuinely significant for the island. When it's finished, the causeway will have its first dedicated bike lane, its first dedicated transit shoulder, a seawall cap built for water levels the 2003 bridge wasn't designed around, and three signalized intersections where informal right of way has governed the flow on and off Bird Key for more than twenty years. The bridge that reopens will do more than the one that's currently torn up, which is a different outcome than simply putting things back the way they were.
For now, the most useful thing a resident can do is treat the RoadWatch page as the weekly source of truth rather than any single estimate, budget extra time around Golden Gate Drive and the Ritz-Carlton crosswalk, and expect the disruption to run through the balance of 2026 and into early 2027 rather than wrapping on a single fixed date.
If you're weighing a move to Bird Key, or you already call the island home and have questions about how a project like this affects daily life, resale timing, or anything else specific to this stretch of Sarasota Bay, the team at Thompson Group Sarasota knows this corridor well enough to talk through it in plain terms. Schedule a private consultation whenever you're ready.